Business operations & real-estate kernels

Queueing/inventory/LP-scoring formulas, earned-value and PERT project math, real-estate underwriting ratios and mortgage amortization, and telecom link-budget/traffic-engineering formulas -- four inde

Four small, independent formula libraries that each cover one back-office domain in a screen's worth of closed-form arithmetic: operations_research (queueing theory, inventory-order sizing, and scorekeeping formulas that share names with, but do not implement, linear-program and transportation-problem solving), project_management (earned-value management, PERT three-point estimation, and a "critical path" function that is a pass-through, not a scheduling algorithm), real_estate (the cap-rate/GRM/DSCR/LTV ratios and mortgage-payment formula an underwriter runs by hand), and telecommunications (Shannon capacity, Erlang-B blocking probability, and the SNR/BER/link-margin formulas behind a radio or trunk-line link budget). None of the four imports from or is imported by any of the others, and none carries a struct or a status-code range — every function here takes plain Float64 (or, for period counts, Int) arguments and returns a single Float64.

from algenta import MojoRuntime

runtime = MojoRuntime(mode="local")

# D=1000 units/yr, ordering cost $50/order, holding cost $2/unit/yr
runtime.execute("operations_research", "eoq_quantity", [1000.0, 50.0, 2.0])["result"]
# 223.60679774997897 -- sqrt(2*D*S/H), the order size that minimizes ordering + holding cost

# $200,000 principal, 0.5%/month, 360 monthly payments (30-year fixed)
runtime.execute("real_estate", "mortgage_payment", [200000.0, 0.005, 360])["result"]
# 1199.1010503055138 -- P*r*(1+r)^n / ((1+r)^n - 1)

The modules

Module
What it does

operations_research

Linear-program objective scoring (not solving), single-cell and 2x2-tableau transportation-cost sums (not the transportation problem), a 3-task assignment-cost sum (not the assignment problem), EOQ order quantity and total cost, the newsvendor critical ratio, Little's Law in both directions, server utilization, and M/M/1 expected queue length and wait time.

project_management

Earned-value management: EV, SV, CV, SPI, CPI, EAC, ETC, VAC, and TCPI; PERT three-point estimation; task float; and a critical_path_duration that is a pre-summed pass-through, not a precedence-graph algorithm.

real_estate

Investment-property underwriting ratios (cap rate, gross rent multiplier, cash-on-cash return, DSCR, LTV, break-even ratio, price per sqft), NOI, a closed-form fixed-rate mortgage payment, equity build-up from amortization, appreciation, and a simplified single-cashflow IRR approximation.

telecommunications

Shannon channel capacity, Erlang-B blocking probability, BPSK bit-error rate, spectral efficiency, link margin, thermal noise power, SNR (linear and dB), Nyquist data rate, propagation delay, throughput, and availability percentage.

operations_research: queueing and inventory formulas, plus LP/transportation scorekeeping, not solving

Function
What it does

simplex_objective_value_2(c1, x1, c2, x2)

c1*x1 + c2*x2 — evaluates a candidate point, does not search for one.

simplex_objective_value_3(c1, x1, c2, x2, c3, x3)

c1*x1 + c2*x2 + c3*x3 — same, three variables.

transportation_cost(cost, allocation)

cost * allocation — one cell of a shipping tableau.

total_transportation_cost_2x2(c1, a1, c2, a2, c3, a3, c4, a4)

Σ(c_i * a_i) over four fixed cells — the caller supplies both the costs and the (already decided) allocations.

assignment_cost_3(c1, c2, c3)

c1 + c2 + c3 — the total cost of an assignment that has already been made for 3 tasks.

eoq_quantity(demand, ordering_cost, holding_cost)

sqrt(2*D*S/H) — the classic economic-order-quantity formula.

eoq_total_cost(demand, ordering_cost, holding_cost)

sqrt(2*D*S*H) — total annual ordering + holding cost at the EOQ.

newsvendor_critical_ratio(cu, co)

cu / (cu + co) — the critical fractile for a single-period stocking decision.

little_law_l(lambda_rate, w)

L = λ * W — expected number in a system.

little_law_w(l, lambda_rate)

W = L / λ — expected time in a system.

utilization_factor(arrival_rate, service_rate)

ρ = λ / μ.

mm1_expected_queue_length(rho)

Lq = ρ² / (1 - ρ); 0.0 if ρ is NaN, infinite, negative, or >= 1 (an unstable queue is reported as empty, not infinite).

mm1_expected_wait_time(rho, mu)

Wq = ρ / (μ*(1-ρ)); same degenerate-input guard, plus 0.0 if μ <= 0.

None of the four names that sound like OR solvers actually solve anything. Reading operations_research.mojo's own docstring and every function body above confirms it: simplex_objective_value_2/_3 only compute Σ(c_i * x_i) at a point the caller already picked — there is no pivoting, no feasibility search, nothing resembling the simplex algorithm despite the name. transportation_cost and total_transportation_cost_2x2 likewise only sum cost * allocation over cells the caller has already decided how to fill; there is no supply/demand balancing and no size beyond the hardcoded 2x2 case. assignment_cost_3 sums three costs the caller has already matched to three tasks. This is a real, checkable difference from Combinatorics, convex optimization, and scipy-compatibility kernels's linear_programming module, which does solve: linear_programming.lp_solve_2var runs vertex enumeration to find an optimal (x, y), and linear_programming.transportation_cost — same bare function name as the one in this module, different signature and different job — runs the Northwest-Corner method over arbitrary-size supply, demand, and costs arrays to produce a feasible (not optimal) shipping plan. Calling operations_research.transportation_cost(cost, allocation) with a single (cost, allocation) pair when what was wanted was linear_programming.transportation_cost(supply, demand, costs)'s multi-cell solver produces a plausible-looking number for the wrong problem.

A worked queueing chain, using the exact inputs tests/mojo/test_wave68.mojo pins: a single M/M/1 server at ρ = 0.8 (λ = 4, μ = 5) has utilization_factor(4.0, 5.0) = 0.8, mm1_expected_queue_length(0.8) = 0.8² / 0.2 = 3.2 customers waiting on average, and mm1_expected_wait_time(0.8, 5.0) = 0.8 / (5 * 0.2) = 0.8 time units in queue. Halving the utilization to ρ = 0.2 collapses the queue by more than a factor of ten — mm1_expected_queue_length(0.2) = 0.04 / 0.8 = 0.05 — the quadratic-over-linear shape of the M/M/1 formula, not a linear one, is why utilization above roughly 0.8 is where queueing systems are usually kept from operating.

project_management: EVM, PERT, and a critical path that is a pass-through

Function
What it does

earned_value(bac, pct_complete)

EV = BAC * pct_complete / 100.

schedule_variance(ev, pv)

SV = EV - PV.

cost_variance(ev, ac)

CV = EV - AC.

schedule_performance_index(ev, pv)

SPI = EV / PV; 0.0 if pv == 0.

cost_performance_index(ev, ac)

CPI = EV / AC; 0.0 if ac == 0.

estimate_at_completion(bac, cpi)

EAC = BAC / CPI; 0.0 if cpi == 0.

estimate_to_complete(eac, ac)

ETC = EAC - AC.

variance_at_completion(bac, eac)

VAC = BAC - EAC.

to_complete_performance_index(bac, ev, ac)

TCPI = (BAC - EV) / (BAC - AC); 0.0 if the denominator is 0.

critical_path_duration(task_durations_sum)

Returns its one argument unchanged.

float_time(late_finish, early_finish)

Float = LF - EF.

pert_estimate(optimistic, most_likely, pessimistic)

E = (O + 4M + P) / 6.

critical_path_duration is a pass-through, not a critical-path algorithm. Its own docstring says as much: "CP = sum (pass pre-computed sum)", and the body is a bare return task_durations_sum — the caller is expected to have already walked the task network and summed the durations along its longest path before this function ever runs. That is a genuinely different job from Routing, scheduling & trade-offs's optimization.scheduling.rcpsp_bound_flat, which takes the actual precedence graph (pred_from, pred_to) and per-activity resource demands, computes the longest path itself, returns which operations are on it (critical_ops), and additionally accounts for resource contention the precedence-only path can't see. A caller that wants "what is the project's critical path" needs rcpsp_bound_flat; critical_path_duration only echoes back a number someone else already computed.

pert_estimate computes the deterministic three-point mean, not a PERT distribution sample. It is easy to confuse with distributions.sample_pert (documented in Probability distributions and dependence kernels), which draws a random value from a Beta-PERT distribution fitted to (min, mode, max, lambda). pert_estimate(optimistic, most_likely, pessimistic) returns the same single weighted-average number every time for the same three inputs — pert_estimate(2.0, 5.0, 14.0) = (2 + 20 + 14)/6 = 6.0, always 6.0 — where sample_pert returns a different stochastic draw on every call. One is the textbook point estimate a project plan reports; the other is a Monte Carlo input for simulating schedule risk.

A full earned-value pass, hand-verified against the formulas above (values chosen independently of the pinned test cases, so this exercises the chain rather than repeating it): a project with a $500,000 budget at completion (BAC), 42% complete (EV = 500000 * 0.42 = 210,000), planned value PV = 230,000, and actual cost AC = 240,000:

Both variances are negative and CPI < 1.0, so the project is simultaneously behind schedule and over budget; EAC ($571,429) exceeds the original $500,000 budget by exactly -VAC ($71,429) — the two numbers are definitionally the same gap seen from opposite ends, which is a useful self-check on any EVM chain built from these functions.

real_estate: underwriting ratios and a closed-form mortgage

Function
What it does

cap_rate(noi, property_value)

NOI / Value * 100; 0.0 if |value| is near zero.

gross_rent_multiplier(price, annual_rent)

Price / Rent; 0.0 if rent is near zero.

cash_on_cash_return(annual_cashflow, total_invested)

CF / Invested * 100; 0.0 if invested is near zero.

debt_service_coverage(noi, annual_debt_service)

NOI / ADS; 0.0 if ADS is near zero.

loan_to_value(loan_amount, property_value)

Loan / Value * 100; 0.0 if value is near zero.

net_operating_income(gross_income, vacancy_rate, operating_expenses)

GI*(1-VR) - OE.

mortgage_payment(principal, monthly_rate, n_months)

P*r*(1+r)^n / ((1+r)^n - 1); principal / n_months (straight-line) if rate <= 0 and n_months > 0; 0.0 if n_months <= 0.

price_per_sqft(price, sqft)

Price / SqFt; 0.0 if sqft is near zero.

break_even_ratio(operating_expenses, debt_service, gross_income)

(OE + DS) / GI * 100; 0.0 if income is near zero.

internal_rate_of_return_approx(initial, cashflow, years)

(cashflow/initial)^(1/years) - 1; 0.0 if initial is near zero, years <= 0, or the ratio is non-positive.

equity_buildup(original_loan, remaining_loan)

Original - Remaining.

appreciation_value(initial_value, annual_rate, years)

PV * (1+r)^years; returns initial_value unchanged if years <= 0.

internal_rate_of_return_approx is a two-point CAGR, not a multi-cashflow IRR solver. A real IRR finds the discount rate that zeroes the NPV of a whole series of periodic cashflows; this function only ever sees a single initial outlay and a single terminal cashflow, and computes the compound annual growth rate between the two — correct for "I put in X, I got out Y, n years later, and nothing happened in between," and not a substitute for a real cashflow-series IRR when there were interim distributions.

A full underwriting chain on one hypothetical property — purchase price and appraised value $950,000, gross income $120,000/yr, 6% vacancy, $42,000/yr operating expenses, 75% LTV financed at 6.5%/30-year fixed — hand-computed and independently verified in Python against the formulas above (no pinned test covers this exact combination, so treat these as a worked derivation, not a quoted fixture):

DSCR = 1.31 clears the 1.20-1.25 floor most commercial lenders require; break_even_ratio = 80.03% says gross income could fall by roughly a fifth before operating expenses and debt service together consume all of it. Five years of 3.5%/yr appreciation on the same property — appreciation_value(950000.0, 0.035, 5) — compounds to $1,128,301.99, and because that is the only cashflow event in the holding period, feeding the same two numbers into internal_rate_of_return_approx(950000.0, 1128301.99, 5) recovers 3.5% exactly, which is the correct self-check for a CAGR formula being fed a pure compounding scenario back at itself.

Function
What it does

shannon_capacity(bandwidth, snr)

C = B * log2(1 + SNR) bits/s; 0.0 if bandwidth <= 0.

erlang_b(n, a)

Erlang-B blocking probability for n trunks under offered load a Erlangs, via the exact recursive form 1/B(k) = 1 + (k/a)/B(k-1).

bit_error_rate_bpsk(snr_linear)

BER ≈ 0.5 * exp(-SNR) (simplified BPSK approximation); 0.5 if SNR is negative.

spectral_efficiency(data_rate, bandwidth)

η = R / B bits/s/Hz; 0.0 if bandwidth <= 0.

link_margin(rx_power, rx_sensitivity)

Prx - sensitivity, in dB.

thermal_noise_power(bandwidth, temperature)

N = kTB, k = 1.38e-23 J/K.

signal_to_noise_ratio(signal_power, noise_power)

S / N; 0.0 if noise <= 0.

snr_db(snr_linear)

10 * log10(SNR); 0.0 if SNR <= 0.

data_rate_nyquist(bandwidth, levels)

R = 2*B*log2(M); 0.0 if bandwidth <= 0 or levels <= 1.

propagation_delay(distance, speed)

distance / speed; 0.0 if speed <= 0.

throughput(data_bits, total_time)

data_bits / total_time; 0.0 if time <= 0.

availability_percentage(uptime, total_time)

uptime / total_time * 100; 0.0 if time <= 0.

None of this overlaps with the two other modules named around "network" in this corpus. Networking and social-graph kernels documents network_protocol (HTTP status-code text, MIME-type lookup, query-string parsing — no socket, no packet) and network_analysis (undirected-graph metrics: PageRank, centrality, connected components — no signal, no channel). telecommunications is a third, disjoint thing again: every function above operates on a physical or statistical-traffic quantity — bandwidth in Hz, SNR, Erlangs of offered load, propagation speed — and none of its twelve functions takes an adjacency list, a URL, or an HTTP status code as an argument. Grepping mojo/engine/telecommunications.mojo and network_protocol.mojo/network_analysis.mojo confirms neither imports the other, and no function name collides across all three modules.

erlang_b's recursion is the textbook one, verified by hand. The classic Erlang-B recursive formula is B(0) = 1, B(k) = a*B(k-1) / (k + a*B(k-1)); taking the reciprocal gives `1/B(k) = 1

  • (k/a) * (1/B(k-1)), which is exactly the loop the source runs (inv_b = 1.0 + inv_b * i / a, starting from inv_b = 1.0). tests/mojo/test_wave84.mojopinserlang_b(0, 5.0) = 1.0(zero trunks blocks every call) and assertserlang_b(10, 5.0)falls between0.0and0.05; re-running the recursion by hand gives erlang_b(10, 5.0) = 0.018384570336648136— ten circuits carrying 5 Erlangs of offered traffic block about1.84%` of attempts, consistent with published Erlang-B tables for that trunk group.

A link-budget chain, hand-computed and verified independently: a 20 MHz channel at 290 K (room-temperature receiver) has a thermal noise floor of thermal_noise_power(20e6, 290.0) = 1.38e-23 * 290 * 20e6 = 8.004e-14 W. A received signal of 2e-13 W against that floor gives signal_to_noise_ratio(2e-13, 8.004e-14) = 2.4988 (linear), or snr_db(2.4988) = 3.977 dB, and shannon_capacity(20e6, 2.4988) = 20e6 * log2(3.4988) ≈ 36.14 Mbit/s — the maximum error-free rate that channel can theoretically carry at that SNR, before any modulation or coding overhead.

Verification

All four mojo/tests/libs/test_*.mojo files for this batch (test_operations_research.mojo, test_project_management.mojo, test_real_estate.mojo, test_telecommunications.mojo) are auto-generated coverage smoke tests: every function is called once with the literal argument 0.5 for every Float64 parameter (0.5 also stands in for the one Int parameter each of erlang_b and real_estate's three Int-typed functions — mortgage_payment, internal_rate_of_return_approx, appreciation_value — actually receive the literal 5) and the test only checks the result is finite — none of the four pins a specific numeric output. The real, hand-derived numeric assertions for this batch live instead in tests/mojo/test_wave68.mojo (operations_research, alongside seismology and photonics; 18 _assert(...) calls across the 17 OR-specific test functions), tests/mojo/test_wave76.mojo (real_estate, alongside metallurgy and game physics; 12 test_* functions, one per public function, most pairing a normal case with a zero-guard check), tests/mojo/test_wave96.mojo (project_management, alongside timber and spectroscopy — its own header calls out "70+ assertions" across all three modules), and tests/mojo/test_wave84.mojo (telecommunications, alongside composites and demographics; 25 assert_true(...) calls inside test_telecommunications(), though the file's own trailing print on that function claims 28 — the discrepancy is in the source's comment, not in this page's count, which was obtained by grepping the function body directly). Every specific number quoted on this page traces to one of those four wave files or to an independent Python re-derivation of the formula from mojo/engine/{operations_research,project_management,real_estate,telecommunications}.mojo, noted inline above wherever it isn't a pinned test value.

Next: see the real LP solver and Northwest-Corner transportation heuristic these formulas are often confused with in Combinatorics, convex optimization, and scipy-compatibility kernels, the precedence-and-resource critical path in Routing, scheduling & trade-offs, or browse the Runtime library catalog for every module and function.